Hi all,

 

The following products will have an update available during the month of May. Below are key highlights for each release. For more information, please refer to the corresponding product documentation for additional details and visuals of the newly added features once the product becomes available.

 

Primavera P6 EPPM v18.5

 

P6 version 18.5 now allows our P6 Professional Clients to install multiple versions of P6 on the same computer. This improvement will enable our Cloud customers to upgrade their stage environment to a newer version for testing purposes before upgrading in Production.

 

P6 v18.5 also improves the integration with Prime's Lean Tasks. Using the Gateway integration, Tasks from Prime are now created and displayed in a new Task tab in P6 so that Project Managers can directly see and react to the impacts that Tasks have on the project schedule. This functionality is available in P6 Web and Client.

 

Two additional BI Publisher reports have been added to help P6 Administrators understand how and when users are accessing P6.

 

 

Textura Payment Management v18.5

 

Textura Payment Management now supports the ability for Owners to add projects to the application. This improvement is part of a broader initiative to add Owner functionality and controls and supports Operational Integration requirements.

 

This release also provides the ability for users to modify subcontract invoice numbers to correct integration errors and reduce support burden. For reports, organizations can now easily extend access to report on all projects using the “View All Projects” permission.

 

 

Oracle Prime Projects v18.5

 

Improvements to Support ‘Idea to Proposed Project’ Workflows

Users will be able to create proposed projects from ideas.  Idea information can now be mapped to fields on the new project object that is created.  To simplify the user experience, Prime now supports the option for a proposal workflow to be automatically linked (no selection required) during the proposal creation step.  We also now allow portfolio query refreshing as part of a workflow, ensuring that any project changes made by the running workflow are automatically reflected in the relevant portfolios.

 

New Subject Areas Available in Charts and Dashboards

The following new subject areas are available for charts and dashboards:

  • Field (Issues, Inspections, Commissioning)
  • Strategies

 

 

Primavera Submittal Exchange v18.5

 

Submittal Exchange now supports users added in bulk from an Excel document. User details can be added (including email, company, role and title) as well as project data including the logs, sections and categories a user has access to as well as email settings.

 

Functionality for project representatives to upload their project specification documents has previously been done via a third party website. This functionality now resides within Submittal Exchange.

 

 

Primavera Analytics v18.5

 

Primavera Analytics 18.5 introduces the following new features:

  • More granular Unifier staging update options that allow for more frequent data updates to Primavera Analytics. Options are 4, 6, 8, 12 hours as well as daily. The ETL will need to be configured in conjunction with the Staging frequency.
  • Revised Admin dashboard to incorporate Unifier metrics alongside P6 (such as Last Logged In, Number of Logins, etc.).

 

 

Primavera Portfolio Management (OPPM) v18

 

OPPM version 18 is built upon an updated Microsoft .NET Framework (4.5) which will provide significant long-term benefits for OPPM customers with respect to performance, memory management and security. This release also includes an number of highly requested feature enhancements.

 

 

Primavera Unifier v18.5

 

In this release, Unifier is introducing Earned Value Management. The source of the data is from P6 integrated via Gateway and stored in the Activity Sheet. Earned Value provides the ability to consolidate multiple P6 projects into one Unifier project. Unifier provides additional costing capabilities including the ability for project level resource and role rates. The Earned Value Analysis provides standard graphs and earned value indices.

 

In this release we are also starting to introduce UDR permission aware data sources. This functionality begins with support for business processes.

 

Project Mailbox now includes the ability to define sub-folders which are associated to their own email address.

 

This release continues with supporting more business process types with the new user interface. The new types that are supported include:

  • Cost with Fund Code
  • Cost with CBS and FBS Code
  • Cost with CBS Base Commit, Change Commit and Invoice with Generic Spends

 

Thanks,

Ron

Hi all,

 

Oracle Industry Connect 2018 has concluded, and if you missed it, we have the highlights!

 

Day 1 blog post

Day 1 video

Day 2 blog post

Day 2 video

 

Thanks,

Ron

Hi all,

 

The following products will have an update available during the month of April. Below are key highlights for each release. For more information, please refer to the corresponding product documentation for additional details and visuals of the newly added features once the product becomes available.

 

Oracle Prime Projects v18.4

 

Reports Platform

In 18.4, The Reports Editor has an entirely new design to improve the overall user experience for creating and modifying reports.

 

Leveraging the existing subject areas as before, column selection and layout design are vastly improved. Choose to work between the Canvas layout view (for Prime Layout reports) or List layout view (for BIP Layout reports). Additionally, codes are now available for grouping and filtering within Main Subject Areas and bar charts and status meter charts now support Count and Sum aggregation types.

 

Field Enhancements & Configuration Packages

Prime Field now supports Linear inspection form functions in Field - Web, to complement the linear inspection forms function in Field for iOS.

  • Create Linear Inspection forms without a Smart PDF:  Currently, Field can generate linear inspection forms from a Smart PDF Form, and display these forms on the Field for iOS app.  With this release, the user will be able to create a Linear Inspection Form without the Smart PDF form.
  • View Linear Forms in the Field Web interface:  Before this release, Linear Forms were only viewed on the iPad.  Now, the Inspection forms on the web will  display Linear Forms as well as PDF Inspection Forms.

 

Also, project Based configuration packages will now include Prime Field configurations.

 

Workflow and Forms for Ideas and More

We continue to build our functionality to support Prime object use cases.  This release provides the ability to review workflow tasks directly in the application object listing pages.  We also continue to enhance the custom forms and workflows for ideas, specifically by adding the ability to add users as task performers and providing more fields options for automatic decision steps.

 

Prime Projects Mobile

Prime Projects, the new mobile application to monitor the health and performance of projects will also be available on the Android operating system in 18.4. Note that Prime Projects for iOS is now available in the Apple App Store.

 

 

Primavera P6 EPPM v18.4

 

P6 version 18.4 includes further improvements in the removal of applets. Applets are now disabled by default for all new deployments of P6. The Portfolio Scorecard has also been re-written using HTML5.

 

 

Primavera Unifier v18.4

 

In this release of Unifier the enhancements focus on two main areas. The first being the Document Manager where we have added the ability to rename documents and to be able to restore an early release of a document as the latest version. The second is the new BP User Interface now supports Cost Type BP with a sub-type of Line Items with CBS Code and the Classification of Generic or Transfer. The new UI also includes changes to the Picker UIs and the ability to group lines. For more details on this release please view the What's New document.

 

 

Primavera Submittal Exchange v18.4

 

Enhanced log preferences are introduced allowing a couple of changes to review logs when subcontractors aren't used on the project. This includes adding the ability to disable the subcontractor column and added the ability to turn off the "return" option in the review logs so users don't have to return items. The Event History page has also been updated to ensure all events are recorded properly - including showing previous and new values.

 

 

Instantis EnterpriseTrack v18.4

 

The 18.4 release features key bug fixes plus one new report focused on the proposal and initial project team membership.

 

Thanks,

Ron

Hi all,

 

Are you subscribed to the Construction and Engineering newsletter? Targeted towards project portfolio management professionals, access the latest white papers, customer stories, event information, and more. This past quarter, the focus was on Integrated CPM and Lean scheduling.

 

To subscribe, please use this link: Subscribe to the Construction and Engineering Newsletter

 

Thanks,

Ron

Hi all,

 

The following products will have an update available during the month of March. Below are key highlights for each release. For more information, please refer to the corresponding product documentation for additional details and visuals of the newly added features once the product becomes available.

 

Oracle Prime Projects v18.3

Lean Enhancements

In 18.3, Lean features a major usability enhancement by providing users the ability to select multiple Tasks in the Hopper and Planning Board and cut, copy, paste, drag and drop them. This release also features an interactive Gantt allowing users to change the due date and duration of Tasks from the Gantt view. Finally, the analysis page just got a little more powerful with Company PPC over Time.

 

New! Prime Projects for iOS

Using the new Prime Projects app, project team members can monitor tasks and activities, access files and communicate with other projects users in a single tap. With a project centric approach and KPIs, monitoring project health has never been easier on-the-go with a data driven overview page that features task and activity progress, tasks by company and missed commitments. With an intuitive navigation, users can access a view of their lean task work plan to monitor tasks and activities that fall within a three-week window. Finally, project files are available on-demand while internet connectivity is available with the options to download any file for offline access. This MVP release features Project iOS only, but a comparable Android version is not far behind.

 

Field Commissioning Report

Users will be able to create reports using the Field Commissioning subject areas.  The user will be able to generate reports for the Project and Workspace.  This is considered the MVP for Commissioning reporting

 

Project Creation Enhancements

Create projects without the Workspace hierarchy restrictions. This helps to easily create projects across Production or Non-Production Workspaces and greatly reduces the manual effort to configure and setup similar projects.

 

Documents’ Log Enhancements

User defined fields within custom logs are now available to be used. Emails, app notifications and inbox notifications are now generated to everyone who has access to a that log when an item is uploaded. Users will also be able to import items from an Excel document to populate a submittal log within Documents.

 

 

Primavera P6 EPPM v18.3

P6's Activity View now includes the ability to interactively work with the Gantt chart. Activity bars can be moved, relationships add and edited, and durations can be changed. The Forecast Bar in Capacity Planning can also be moved manually.

 

 

Primavera Analytics v18.3

Primavera Analytics now supports OBI 12.2.1.2.0.

 

 

Primavera Gateway v18.3

In 18.3, Gateway introduces the addition of the user configurable option in Primavera Gateway framework to limit deletion of the data in the target application to only data that was previously synchronized using gateway

 

 

Instantis EnterpriseTrack v18.3

The 18.3 release features key bug fixes plus small additions to the Non-WBS Activity Report and Deleted Records Report to support customer data extract use cases.

 

 

Primavera Unifier v18.3

The latest release of the Unifier Mobile App will also be released which includes the following:

  • Support for user-based locale, region formatting and the supported twelve languages.
  • Users can now choose to use either the time zone of their device or the Unifier server when moving across time zones
  • Copy BP records and line items with or without attachments.
  • Support for split screen display on iPads.
  • Easily search the Documents hierarchy for files and folders.
  • When routing workflow records, expand and select users from the task assignee group as the next step assignees.
  • Support for conditional filtering of step assignees as per the workflow design.

 

Continuing to enhance the new UI BPs including the following:

  • The Project/Shell Creation BP now supports the new UI.
  • The user can now group line items rather than using summary lines. This provides more flexibility than the summary lines.
  • The Linked Mail UI has been updated.
  • Comments have been changed to be similar to the commenting in the Document Review form.
  • When creating a Business Process from the Document Manager that support the new UI, the new UI will be used.
  • Creating templates for Business Processes now has a new UI that reduces the number of popups. For Business processes that support the new UI they will be used in order to create the template.
  • Viewing of attachments within the BP now support the Unifier Viewer as well as AutoVue.

 

A number of enhancements have also been added to the Document Manager:

  • Within uDesigner, we now support the ability to have multiple document and folder attribute forms. These new forms can be assigned to shells on the Options tab.
  • Files are now uploaded asynchronously which allows the user to continue with other work while the documents are uploaded.
  • Like the Business Processes, it is now possible to for the administrator to define the views that users will see within the Document Manager.

 

Support for Financial Periods has now been added to Unifier. The administrator can now define their own periods. These periods can then be assigned to a shell which can then be used when creating cash flow curves. In addition, to the cash flow, the financial period can also be assigned to a Portfolio which will then use the periods to display the columns in the sheet. The Portfolio will also only include projects with the same Financial Periods.

 

Along with the Financial Periods, the Portfolio now supports actuals based on derived curves when displaying the actuals in the sheets.

 

Additional UI Enhancements:

  • The Portal Landing page has a new default layout. For each portal Business Process it will display a pie chart by status a list of the records.
  • The User Preference page has also been updated.

 

The License Manager has now been updated to combine what used to be Company and Partner license counts into one Standard license count. This removes the need for customers to request support to move licenses between Company and Partner users. We are also introducing a license count for Portal users. User will now be defined as either Standard or Portal users and will be validated against the appropriate license count. Portal users will automatically be logged into the Portal.

 

Thanks,

Ron

Hi all,

 

I wanted to highlight some recent changes our Primavera communities have undergone:

 

  • We launched the Oracle Primavera Cloud (MOSC) community to house all content for the Oracle Prime Projects product, including discussions and enhancement requests, also known as ideas. Content for the Prime Projects product that was located in the Primavera (MOSC) community has been migrated to the new community.
  • We have renamed our existing communities to better align our spaces with our products:
    • Primavera (MOSC), the top level space which houses all of our communities is now named: Oracle Construction and Engineering (MOSC)
    • Primavera-PRIM (MOSC), which covers the P6, Instantis, Contract Management, Risk Analysis, Analytics, and Portfolio Management (OPPM) products, is now named: Primavera (MOSC)
    • Unifier-PRIM (MOSC), which covers the Unifier product, is now named: Unifier (MOSC)
    • CPIC-PRIM (MOSC), which covers content with the CPIC module, is now named:  CPIC (MOSC)

 

One important thing to note here is that all existing URLs for all existing content was NOT changed. If you had anything bookmarked, it will still be there.

 

Please let me know if you have any questions about anything.

 

Thanks!

Ron

Hi all,

 

The following products will have an update available during the month of February. Below are key highlights for each release. For more information, please refer to the corresponding product documentation for additional details and visuals of the newly added features once the product becomes available.

 

Oracle Prime Projects v18.2

Custom Logs within Documents

Custom logs allow users to track all project collaboration documents in a log format that make sense to the project team. This type of organization works well for documents, such as meeting minutes, that are being uploaded and do not require a workflow.

 

Field Reporting

Subject Areas for Field Issues, Inspections, and Commissioning are now available for Prime Reports. As with all reporting subject areas, these are available for both Prime and BI Publisher Layout designs.

 

Prime Progress Mobile File Access

Partners and vendors using Oracle Prime Progress for both iOS and Android will now have on-demand access to their project files from their mobile device. Users can browse, view and save project files to their device for offline access.

 

Work Plan Multi-Week Printing

Two-week or three-week rolling schedules are very common in the construction industry. The Work Plan page of the Tasks app has been updated to allow multi-week printing on a single page width.

 

 

Primavera Unifier v18.2

The Summary Payment Application has been enhanced to allow the user to enter a value greater than 100% in the % Complete column. In order to still retain control on what can be paid we had implemented the Commits Remaining Balance functionality that is currently available in the other Payment Application. We have also added the ability to define how the values on the summary rows should roll up from the cost breakdowns.

 

Within the Business Process setup we have now added the ability to filter the list of CC users to match what is available for assignees. We have also added the ability to use an OR condition across all the queries for both the assignees and the CC users.

 

In this release we are continuing to enhance the Business Process UI with updates to the Query Based Tabs, Reference Records, Line Item Consolidation, Comments and Attachments.

 

We are also continuing to enhance the Document Manager by giving the user the ability to revise or keep both when copying a document to a folder that already contains a document with the same name.

 

For integration, we have extended the getSOV web service to also support the Summary Payment Application type of Business processes.

 

Lastly, we have added a new Administrator menu option that allows them to view the background jobs that are scheduled to run. As well as being able to view the jobs, the administrator can also define which time zone should be used when the job is next scheduled.

 

 

Primavera Analytics v18.2

Primavera Analytics now supports several Unifier pickers and data pickers which can be configured in the Unifier > Administration Mode > Analytics > Business Processes. The following pickers and data pickers are supported:

 

  •     BP Data Picker
  •     Shell Data Picker
  •     Space Data Picker
  •     User Data Picker
  •     BP Picker
  •     User Picker
  •     Shell Picker
  •     Space Picker 

 

 

Primavera P6 EPPM v18.2

P6 version 18.2 introduces the ability to directly integrate Prime's Lean Tasks with P6's Steps. Using the Gateway integration, Tasks from Prime are now created as Steps in P6 so that Project Managers can directly see and react to the impacts that Tasks have on the project schedule. This task integration is only available on web only in 18.2, equivalent functionality to be delivered for client in the coming months.

 

To improve usability, customers now have the ability to assign EPS, Activity, and Resource Assignment views to specific users rather than all users. Version 18.2 also includes a new Earned Value field - Performance Percent Complete - Labor Units. This new field is calculated as Earned Value Labor Units divided by Budget at Complete Labor Units multiplied by 100.

 

 

Primavera Gateway v18.2

Primavera Gateway version 18.2 further enhances pre-built integration between Prime and P6. In this release we added support for Lean Task flow by allowing Prime tasks to be mapped with P5 Activity Steps. This is on directional OOTB flow to provide visibility to P6 project manager with the latest statuses form Prime Tasks.

 

We added ability to automatically clean-up synchronization job logs in Primavera Gateway. Primavera Gateway Administrators can now set configurable parameter that will specify number of days that the job log should be retained. After specified number of days, the system will automatically remove job logs older than provided threshold.

 

Added support for P6 Activity code hierarchy transfer when duplicate code values exists within different parts of the three.

 

 

Primavera Submittal Exchange v18.2

Submittal Exchange enhances the custom role label functionality to be controlled at a log level instead of at a project level.

 

 

Instantis EnterpriseTrack v18.2

This release includes several bug fixes as well as a Proposal/Project Finance Search API enhancement and a new column "Hours per Week" in the Resource Listing Report.

Hi all,

 

We have recently created video content in our Knowledgebase, centered around the technical aspects of P6. Please check them out below:

 

  • How to Configure SSL in WebLogic 12c Using the Demo Keystore for P6 EPPM [Video] (Doc ID 2331396.1)
  • How to Create a WebLogic 12c Managed Server for P6 EPPM [Video] (Doc ID 2331397.1)
  • How to Do a Session Trace on P6 Professional Connected to an Oracle 12c Database Using DBMS Support [Video] (Doc ID  2331420.1)
  • How to Download, Install, and Upgrade Primavera P6 Professional 17.7.0.0 [Video] (Doc ID 2331432.1)
  • How to Reset Database and Application User Passwords in Primavera P6 [Video] (Doc ID 2331434.1)
  • How to Upgrade a Primavera P6 SQLite Database [Video] (Doc ID 2331435.1)
  • How to Use SQLite Editor on a Primavera P6 Standalone (SQLite) Database [Video] (Doc ID 2331427.1)

 

Hope these are helpful.

 

Thanks!

Ron

Hi all,

 

The following products will have an update available during the month of January. Below are key highlights for each release. For more information, please refer to the corresponding product documentation for additional details and visuals of the newly added features once the product becomes available.

 

 

Oracle Prime Projects v18.1

 

New Navigation

Prime 18.1 has updated Prime’s Navigation geared towards simplifying Prime and how users understand or interact with the system. Updates include; switching the primary navigation element to the Object (Project, Portfolio, Workspace), a browse fly-out for that primary element, moving the Object’s functionality (Schedule, Risk, Tasks, etc…) to the left side within those objects, new on-boarding elements and an improved Search.

 

Ideation Additions

In this release we add evaluation scoring and investor maps to our existing idea objects and allow then to be routed to idea owners for review and approval. A short training video is available by clicking here.

 

 

Primavera Unifier v18.1

 

With this release we have added several new enhancements to the document manager.

  • Thumbnail view allows the user to be able to view the content of folders based on thumbnails of supported file formats.
  • Search has been extended to include searching based on document meta data.
  • Shortcuts and favorites have been added to allow users to navigate quickly to the folders and files they commonly use.
  • For administrators, we have now added the ability to push folder structures and permissions from templates out to shells.
  • A new DE has been added that can display the URL for the document.

 

Included in this release is also the start of the new user experience for the Business Processes. This is currently limited to non-production environments for the initial release and to Simple and Generic Line Item type Business Processes.

 

In Portfolio Manager we have made some usability enhancements to the UI including the ability to edit fields to the left of the split and being able to define the widths of the columns. We have also introduced the ability to notify users in a project whenever a Scenario is shared or approved.

 

A number of forms have also been updated to reflect the user experience that is available in the logs. These include:

  • Home Landing Page
  • All the Mail related forms
  • Portal Landing Page
  • Bidder Portal

 

Within Analytics we have now included support for CBS text attributes, line item tab identifier and increased the number of fields that can be extracted for BPs and Shells.

 

Based on customer feedback, we have also made changes to the adding of tabs for projects. This has been reduced to a single tab where the user can see a list of their recent projects, their bookmarks, key locations and can also search for projects. We now also allow the administrator to define if the number or name of the shell should be displayed in the tab.

 

Within the Summary Payment Application we have now added the ability for the administrator to define how the values from the summary rows should display on the total row on the bottom of the form. The options include sum, formula and blank.

 

In order to reduce confusion between P6 WBS codes and Unifier cost codes, Unifier has been updated to display CBS rather the current WBS.

 

 

Primavera Analytics v18.1

 

Primavera Analytics version 18.1 introduces several new features for both Primavera P6 and Unifier customers.

  • For Unifier, support for up to 20 CBS text data elements for use within Primavera Analytics, providing additional insight into Unifier cost data.
  • Historical Unifier fact data can now be captured in monthly intervals, providing greater flexibility in how historical data and trending can be analyzed.
  • The sample catalog includes several Unifier mobile analyses based on OBI’s Mobile App Designer. These samples support cost sheet, cash flow, and BP analyses and are supported on any HTML-5 compatible mobile device.
  • A new 'What-If' dashboard page is now in the sample catalog giving users the ability to model potential P6 project changes.
  • Customers can now increase the number of P6 UDFs, P6 codes, and Unifier BP data elements up to the documented maximum without submitting a request to Oracle Support (for cloud customers) or manually editing the Oracle BI .rpd file (for on-premise customers).
  • ETL Data Source names can be customized directly in the web-based Primavera Analytics Administration module.
  • P6 and Unifier Action Link URLs can be configured directly in the web-based Primavera Analytics Administration module or through the Primavera Data Warehouse Configuration Utility.

 

 

Primavera P6 EPPM v18.1

 

P6 version 18.1 includes usability enhancements that will improve efficiency and performance.

 

P6 Professional release 18.1 includes a comprehensive caching mechanism for Cloud Connect environments, Primavera Cache Service. Primavera Cache Service greatly enhances the user experience by making the most frequent operations near instantaneous: adding, deleting, and updating a single activity.

 

P6 Web Activity view now has the ability to copy multiple WBS nodes at one time and also includes a new and improved Progress Spotlight feature. EPS and Resource Assignment Classic views can also be converted to Standard views via Import/Export.

 

 

Instantis EnterpriseTrack v18.1

 

For our first monthly release of 2018 we are introducing two minor enhancements: The first is the addition of more fields to the project listing report.  This is part of an on-going effort to support the extraction of all EnterpriseTrack data.  The second enhancement provides multi-initiative customers with the option to hide program features which may be in use by other initiatives.

 

Thanks!

Ron

Hi all,

 

The following product will have an update available during the month of December. Below are key highlights for the release. For more information, please refer to the corresponding product documentation for additional details and visuals of the newly added features once the product becomes available.

 

Oracle Prime v17.12

 

Enhanced Portfolio Planning Capabilities

The portfolios team has been releasing useful enhancements to resource planning, budget optimization and funding throughout the second half of 2017.  As of 17.12, resource planners can now analyze resource costs based on the role rates. For budget planners, the portfolio evaluation category scores can be optimized using the efficient frontier, funds can now be allocated to portfolios from the workplace fund and the allocation of funds to the optimum solution set requires only one click!

 

Application Presets & User Administration Improvements

Application Administrators can now define a Preset based on which certain applications will be accessible or hidden from the users. Also, a new User Administrator privilege helps certain users to be able to add multiple users in their own company, without depending on the Application Administrators.

 

Production & Non-Production Workspace Support

Prime now supports a clear distinction between the Production and Non-Production workspaces. This makes it easy for the customers to use workspaces for solutioning, testing and training.

 

Thanks,

Ron

Hi all,

 

We are excited to announce the delivery of Prime Progress, a mobile app suited for users that progress and perform critical work assigned to them and their company. With Prime Progress, users can stay current on project site updates and ensure the project team is familiar with the work being completed.

 

The following project-centric features are now available:

  1.     Provide on-site progress updates for work assigned to self or company including tasks and activities
  2.     View and update assigned issues
  3.     Collaborate with peers on assigned work using Prime discussions
  4.     Offline access to multiple projects

 

For the first time in Prime, we are providing comparable functionality on the Android operating system! In recent weeks, we released Prime Progress for both Android and iOS marking a significant milestone in our effort to go to market with feature parity across both mobile platforms.

 

Prime iOS End-of-Life

The mobile team has been busy executing on a plan set forth by the strategy team to increase value to Prime customers with targeted applications like Prime Progress. This targeted approach allows us to deliver functionality to different persona’s in different ways. In light of this shift in strategy, the existing Prime iOS application will be removed from the Apple App Store in early December. For existing clients interested in lean task and activities on mobile, the same feature set is available in Prime Progress.

 

Thanks,

Ron

Hi all,

 

Are you using the Cloud and are unsure of how to manage your users? Or are you interested in the Cloud and wondering how user administration differs from an on- premise deployment? If so, check out this recently created Knowledge document which links to a video created by our curriculum team.

 

How to Manage Users in the Primavera Cloud Administration Application [Video] (Doc ID 2325447.1)

 

This document provides a video tutorial for managing users in the Primavera Cloud Administration Application, including instructions on how to:

  •     Add Users
  •     Manage their accounts and application access
  •     Create Partner Companies

 

Thanks!

Ron

Hi all,

 

The following products will have updates available during the month of November. Below are key highlights for each release. For more information, please refer to the corresponding product documentation for additional details and visuals of the newly added features once the product becomes available.

 

Oracle Prime v17.11

 

New! Prime Progress for Android

For the first time in Prime, mobile users will have comparable functionality, no matter which operating system they prefer! Like Oracle Prime Progress for iOS, Android allows users to monitor and progress critical work assigned to them like tasks, activities and issues. This ensures project workers will stay up to date with project site updates and ensure the project team is familiar with the work that has been completed. 

 

Create and Edit Field Inspections on the Web

Users will be able to create, edit and progress inspections through the workflow using the Prime Field web interface, complementing the inspections function from the Prime Field for iOS mobile application. Built with a consistent user experience, the behaviors and actions throughout inspection management on the web interface are familiar to users of other Prime applications.

 

Create Projects in P6 from Prime & Platform Improvements

Projects created in Prime can now be set to use Cloud Sync, and will be created in P6 EPPM. Previously, project data only flowed from P6 to Prime. Now, project header data can be synced in both directions. Additionally, user passwords can now be reset by administrators in Prime, negating the need to submit a service request to Support.

 

Improved Document Exchange Reporting and Communication

Submittals and RFI objects are now available for users to report on. Users can create a report by clicking on the Run Report icon at the top of the Submittal or RFI grids, or by going to the Reports module within Prime. Additionally, e-mails are now being sent for Submittal Items that are using the out of the box workflow.

 

 

Primavera P6 EPPM Cloud Service, Analytics & Data Warehouse v17.11

 

17.11 provides hybrid support between P6 EPPM Cloud Service and an on-premise instance of either Primavera Analytics or the Primavera Data Warehouse.

 

As part of the process, the necessary data for the Data Warehouse is copied in near real-time from the cloud-based P6 PMDB to an on-premise P6 PMDB database via the Primavera Analytics Cloud Sync utility.

 

In addition, as part of the Cloud Sync utility, we are providing a P6.jar file to run P6 Publication Services on the on-premise P6 PMDB database. This populates the Extended Schema which then allows a customer to run their on-premise ETL to populate the Primavera Data Warehouse and Primavera Analytics.

 

The Primavera Analytics Cloud Sync Utility is included with either Primavera Analytics or the Primavera Data Warehouse and includes a restricted use license for WebLogic Standard Edition to run the above processes. Note that P6 itself is not supported on the on-premise P6 PMDB copy.

 

Currently, customers must submit a Support Request to obtain the necessary files and documentation. This will be moved to the customer Cloud Admin page starting with v18.

 

 

Primavera Submittal Exchange v17.11

 

17.11 introduces a new grid in the Submittal, Closeout and RFI logs, which addresses several user interface issues clients have been asking for. The new interface allows the users to be able to freeze headers, lock the left column, and displays a delineation between each expected item (which makes reading the logs easier) in Chrome, Firefox and Internet Explorer. The introduction of the new grid also provides users with updated print capabilities, budget totals, the ability to expand or collapse sections and categories, and set up in-column filters. A new email notifications will now be sent out if a photo gallery or one or multiple photos are added, edited, or deleted from a gallery. The frequency of notification emails will follow what the user sets up in their email settings. Several bug fixes were addressed as well.

 

 

Announcing v17.3 for Instantis On-Premise and Cloud Customers

 

In this three-month release, we are making modifications to enable customers to filter and report data based on the last updated time stamps, beyond the existing daily date stamp.  We have also included some smaller enhancement requests.  The evaluation matrix weights can now be edited, proposal finances can be enabled for "single view" templates and the reporting for proposal finances has been improved.  This is the last official release of Instantis for on-premise installations.  In 2018, we are transitioning to a monthly cloud-only release cycle.

 

Thanks!

Ron

Hi all,

 

The following products will have updates available during the month of October. Below are key highlights for each release. For more information, please refer to the corresponding product documentation for additional details and visuals of the newly added features once the product becomes available.

 

Oracle Prime v17.10

 

RFIs Now Available in Prime Web & Field Mobile!

RFIs, Requests for Information, are being introduced in both Prime Field iOS and Document Exchange. A user can create an RFI to assign a question about an open issue to a project team member. Users will be able to view RFIs in a grid, The grid displays information such as status, required action and ball in court. Users  have the ability to attach files, markup files, view the communication trail, and receive automated alerts and notifications.

 

New! Prime Progress for iOS

Oracle Prime Progress for iOS allows users to monitor and progress critical work assigned to them like tasks, activities and issues. This ensures project workers will stay up to date with project site updates and ensure the project team is familiar with the work that has been completed. Oracle Prime Progress for iOS supports offline access. 

 

Improved On-Boarding for New Users!

Prime 17.10 includes a guided tour that walks new users through the setup process. Use the step-by-step walk-through, or take the tour without steps and decide where to begin. This feature helps expedite the setup process, and eliminates the need to spend countless hours reading through a manual.

 

Create and Edit Field Issues Using the Web Interface

Users will be able to create, edit and progress issues through the workflow using the Prime Field web interface, complementing the issue functions from the Prime Field for iOS mobile application. Built with a consistent user experience, the behaviors and actions throughout issue management on the web interface are familiar to users of other Prime applications.

 

Primavera Submittal Exchange v17.10

 

The 17.10 release of Primavera Submittal Exchange includes a new feature that allows an initiator to re-open an item and send it back to the final reviewer in each of the logs that has a review flow (log type 1, 2, 3, 4, and 8). This release also addressed several bug fixes including consistent handling of email links, special characters, and re-enabling the multiple reports option.

 

Textura Pre-Qualification Management v17.10

 

This release of PQM completes our conversation from DB2 to Oracle Database.

 

Thanks!

Ron

Hi all,

 

Java 9 was released on September 21, 2017. The current versions of P6 will not work with Java 9, as it requires code updates to P6.

 

Our schedule for JRE 9 compatible/certified versions of P6 is as follows:

  • 17.10:           Early-October 2017
  • 16.2.10.x:     Mid-October 2017
  • 15.2.16.x:     Mid-October 2017

 

One thing to note is that JRE 9 will NOT auto-update JRE 8 users to JRE 9, so P6 users need not be concerned if auto update is enabled.

 

For more information on this issue, please see: Java 9 Support With Primavera P6 EPPM (Doc ID 2125099.1). This document as well as the Tested Configuration documentation for each product will be updated upon completion of certification testing.

 

Thanks,

Ron