Update 19A Fix: Import External Requisitions containing up to 10000 Lines
Summary
Allow import of external requisitions containing up to 10000 Lines and route for approvalContent
Customer / Support
There is recent fix in 19A that I wished to communicate through this article.
Issue:
Planning system (Planned order releases from Planning Central for instance) tend to have thousands of lines on a requisition. Up until this fix, the system would only process the first 500 lines through approval while the remainder of the lines would stay in Pending Approval.
Fix:
With this fix, such external requisitions containing up to 10000 lines can be processed successfully. The limit has been changed from 500 to 10000.
We get asked this question quite often from support for customers. Even as recently as yesterday, this was discussed on a customer post. I thought it fit to provide this information for support to share the next time this comes up as a customer query.