Accept a lot originally rejected following in line inspection.

Question
6
Views
0
Comments
edited Jan 28, 2021 5:47PM in Quality

Content

Hi all,

We would to know if the following action can be managed between Quality and Inventory
Following in line inspection with a reject a lot rejected and quality issue is open.

After investigation, the deviation is accepted and the lot can be accepted and put away.
Is such action can be handled by quality cloud ?

Thanks for your help !