This discussion is archived
2 Replies Latest reply: Feb 16, 2012 8:44 AM by rm22 RSS

Assigning Committed Proposed Change Items to a Change Mgmt Item (v13.0)

915008 Newbie
Currently Being Moderated
Hello Primavera Community!

I am working on a particular scenario in which I have potential cost changes I would like to first enter into CM as a quoted commitment, then assign to a previously created Change Management line item AFTER I have created the quoted commitment.

From there, my intent is to have the ability to forward the quoted commitment to a quoted/negotiated budget via Change Management, and eventually to a finalized commitment.

Not sure if this may violate some sort of fundamental rule of change management; regardless, I would like to have the ability to do as I have indicated above at times, rather than having to create the Change Management Item first then create the quoted commitments afterwards.

I would appreciate any input you master Jedi's may have. Thank you in advance for your help.

Legend

  • Correct Answers - 10 points
  • Helpful Answers - 5 points