    Milestones: Max Start falling after Max Finish??

    925714
      I am a recent user of PRA and in putting a schedule through a thousand iterations most of the dates came out perfectly fine but after being asked by a project manager to look at 3 milestones, after looking at the duration probabilities of the 3, the first (near the start of the project) had a perfectly normal max finish falling one day after the max start, but the other 2 (at the latter end of the project) were showing that the max start finished a day after the max finish.

      Does anyone have an idea as to why this is happening and the reasons behind it?

      Any help anyone could offer would be greatly appreciated,

      Thanks,

      Scott