Early Start and Early Finish Dates

933585 Newbie
Currently Being Moderated
When I build a schedule I always build it to early start and early finish dates. When I go to update my project the items that are finished always return a blank in the early start and early finish dates. Is there a way to get the program to still show the dates that the activities started and finished on in the early start early finish columns? I would like to be able to use the early start and finish columns instead of having to add more columns to be able to look back and see the start and finish dates for an activity that has already been completed.

Thanks,

Ryan Cherry

Legend

  • Correct Answers - 10 points
  • Helpful Answers - 5 points