    budgted values VS Porject baseline values.

    930504
      hi there...

      after completing my plan and baselined it...i started statusing the schedule against the assigned baseline....during collecting field data i noticed that:

      my actual units were always above my baseline units
      my actual cost were always above my baseline costs.


      based on this...in my activity usage profile... what i expected to see is that:

      the actual units bars are always higher than my the baseline bars..
      the actual cost bars are always higher than my the baseline bars..


      what i saw instead was that:

      my actual bars are some times lesser than the baseline bars (which is something i dont have in my project....in my project the actual are always higher).

      after doing some playing with the activity profile i noticed that:

      comparing the actual bars with the "budgeted bar" gives exactly what i expected..

      this brings up the following question:

      what is the difference between the budgeted values and project baseline values.


      your help would be highly appreciated.


      best regards
        • 1. Re: budgted values VS Porject baseline values.
          924630
          Your budgeted values and baseline values should/could be the same. But if you start changing the current project's budgeted units/costs, they will be different. But since your baseline values aren't giving you the expected results, I would look at Admin Preferences -> Earned Value (tab) -> Earned Value Calculation (drop-down). At Completion Value or Budgeted Values are the 2 choices. Perhaps it's using At Completion Values and those are not the same as the Budgeted Values?