Hi Experts,

I have done following setup in system in order to use shipping calender,

a) Define an item, enable ATP. Now we are having ATP based on ASCP plan output.
b) Define calender where Friday is only working day. This is our shipping calender.
c) Assign shipping calender to customer, with its ship to site in order management.
d) Enter SO line for this item. Enter req date - 02 Jul 12 (Thus-day), assume that item is having very less lead time so it will be complete prior to 02 Jul. But due to request date and shipping calender, schedule ship date should be 06 Jul 12, but it is showing as 02 Jul 12.

So want to know reason behind it.

Thanks in advance / Dipak