2 Replies Latest reply: Aug 20, 2012 1:42 AM by 956045 RSS

    Remaining units calculation

      Hi Looking for some help. In the schedule I am currently working on , I do not want to record actual units against each activity. Is there a way in Primavera to make the remaining labour units = estimate to complete labour units? This would mean as the % complete increases the remaining units automatically decreases. Hope someone can help