    Dates on Sure track 3.0

      Why when I put in a duration date of 3 days it makes my early start to early finish 4 days? For example, I have an early start of 7/16/12 with a duration of 3 days so my early finish should be 7/18/12. Instead I am getting an early finish of 7/19/12. So my vendors think they are getting an extra day. Thank you.