Item (Order) scheduling priority

904961 Newbie
Currently Being Moderated
Hello experts,

i have a question about scheduling priority of a discrete job. Is it available to mark Purchase Order or Item to schedule them as higher priority discrete job then releasing it? By default a schedule priority for every job is 10 (then 10 is the lowest, 1 - highest priority), and I can change it to higher priority only in discrete job options after MRP planning and I want to do it before (then entering Purcase Order for example).

Maybe anyone have ideas.

Thank you