1 Reply Latest reply: Sep 14, 2012 5:21 PM by 924630 RSS

    Copy/Paste between schedules

    JimS-Indy
      P6 8.2 Professional Standalone on a Laptop.

      I have two schedules -- one for the general building, and one for detailed upfit of one floor. Both are in the same EPS, using the same code structure (No resources, No WBS.) All the codes are EPS codes, no Project codes.

      I want to merge them. Basically, I want to bring the single-floor schedule into the main schedule. I've been away from it for awhile. How do I do this?
        • 1. Re: Copy/Paste between schedules
          924630
          Highlight both projects, open them, group by WBS (which will actually be your project), copy all from one and paste to the other. Consider any codes that are project-specific that may not transfer over. Promote those code to EPS or Global if necessary. Do this on copies of the projects first to see if you get the results you want.