    manually updating resource unit

      Looking for some help. In P6 (Project management) I am currently working on, I want to update actual unit of each resources, but i have this situation: Budget unit<Actual Unit , I would like to keep that relation and show overload resource. my question is How can i calculate Remaining unit?. It should be negative but i couldn't define negative value Resources Tab.