MRP Planned Percent

857499 Newbie
Currently Being Moderated
Hello Gurus,

Please can somebody help in understanding the MRP Planned Safety stock calculations

There are "Bucket Days" and "Percent", please help me in unederstading these options and how should i set the "Bucket Days" and "Percent"

Regards
  • 1. Re: MRP Planned Percent
    the-pooh Newbie
    Currently Being Moderated
    Hello..

    the below statement is pick from oracle inventory user guide.
    hope its help.

    Safety Stock Bucket Days
    ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
    Enter the number of days to dynamically calculate safety stock quantities. The planning
    process multiplies the Safety Stock Percent by the average gross requirements and
    divides by the number of days you enter here. See Overview of Material Requirements
    Planning, Oracle Master Scheduling / MRP and Oracle Supply Chain Planning User's Guide.
    Safety Stock Percent
    ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
    Enter the percent to dynamically calculate safety stock quantities for the item. The
    planning process multiplies this percent by the average gross requirements and divides
    by the Safety Stock Bucket Days.
    *6-48 Oracle Inventory User's Guide*
    The planning process uses this attribute when you set Safety Stock to MRP planned
    percent. See Overview of Material Requirements Planning, Oracle Master Scheduling /
    MRP and Oracle Supply Chain Planning User's Guide.