This discussion is archived
6 Replies Latest reply: Nov 8, 2012 9:42 AM by oracle_samba RSS

What is impact of Complex procurment with retention on Oracle Project Cost?

oracle_samba Newbie
Currently Being Moderated
Hello Experts / Dina,

Can you please explain the flow and acrrual of cost when complex purchase order has been raised with multiple retention on Oracle Project and interface the cost to Oracle Project.

Example - Complex purchase order of contract consulting is raised with amount of 1000 GBP with 4 Milstone of 250 GBP upon 25% completion of work.

I wanted to know in this scenarion how the retention payment / invoice matches to purchase order impact on cost interface to project by using PRC:Interface cost to projects.

Thanks in advance,

Regards
:-)

Legend

  • Correct Answers - 10 points
  • Helpful Answers - 5 points