1 Reply Latest reply: Nov 12, 2012 10:00 AM by G V Ranjith RSS

    Update Standard cost for new items

    702114
      We are in 11.5.10.2 and using Standard Costing. We are going to assign new items to one of the inventory organization. These items are sub-assemblies and its components (purchased item) to the already existing Final assembly.

      Now what are the steps I have to do to update the cost?
        • 1. Re: Update Standard cost for new items
          G V Ranjith
          Hi Rajesh,

          I hope all the items you are planning to assign to a new inventory organization are costed in existing organizations.

          You may run the copy costs program to copy the item costs from existing inventory organization to a cost type other than "Frozen" in new inventory organization.

          After the copy is successful, you may run update costs program to update frozen costs in the new invnetory organization.

          Regards,
          G V Ranjith