    MRP Planned Percent

    857499
      Hello Gurus,

      Please can somebody help in understanding the MRP Planned Safety stock calculations

      There are "Bucket Days" and "Percent", please help me in unederstading these options and how should i set the "Bucket Days" and "Percent"

      Regards
        • 1. Re: MRP Planned Percent
          the-pooh
          Hello..

          the below statement is pick from oracle inventory user guide.
          hope its help.

          Safety Stock Bucket Days
          ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
          Enter the number of days to dynamically calculate safety stock quantities. The planning
          process multiplies the Safety Stock Percent by the average gross requirements and
          divides by the number of days you enter here. See Overview of Material Requirements
          Planning, Oracle Master Scheduling / MRP and Oracle Supply Chain Planning User's Guide.
          Safety Stock Percent
          ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
          Enter the percent to dynamically calculate safety stock quantities for the item. The
          planning process multiplies this percent by the average gross requirements and divides
          by the Safety Stock Bucket Days.
          *6-48 Oracle Inventory User's Guide*
          The planning process uses this attribute when you set Safety Stock to MRP planned
          percent. See Overview of Material Requirements Planning, Oracle Master Scheduling /
          MRP and Oracle Supply Chain Planning User's Guide.