    Importing Budgeted labor cost from excel

    1983-PLANNER
      Hi,

      This is regarding updating the budgeted labor cost in excel and importing back to P6.

      I have allocated single resource to my activities and exported to excel with budgeted labor cost column.
      Now when i update the budgeted labor cost and import back the values are not getting updated.

      Any reason why and how to do this?

      Thanks,
      Imad