Resource assignment to multiple activities

1983-PLANNER Newbie
Currently Being Moderated
Sir,

I am trying to assigning single resource "resource name : XYZ" to multiple activities using the option right click, .
After assigning using this option i had a problem with the resource.

Problem is for some activities the resource "XYZ" is getting assigned multiple times.