4 Replies Latest reply: Dec 10, 2012 3:47 AM by 973217 RSS

    Updating Actual cost in P6

    1983-PLANNER
      Hi there,

      I have a histogram / S-curve representing cumulative budgeted cost under activity usage spread sheet. Now i am looking for

      1. A column(in the activity table) showing the planned budgeted cost for each activity up to Data Date.
      2. cumulative actual cost showing in the activity usage spread sheet.

      Is this possible ? so that i can export to prepare s-curve with actual cost..

      Thanks,
      Imad