Revenue Split based on Tasks

936996 Newbie
Currently Being Moderated
Hello All

We have two Billable Top Tasks on a Projects , and we are using cost-Cost distribution rule to generate Revenue based on the cost based on the task, is there a way to generate two separate Revenue accounting Lines based on the cost accumulated on the two task.( Say we use a work type on each task as an identifier for generating Revenue)

Regards
DR
  • 1. Re: Revenue Split based on Tasks
    936996 Newbie
    Currently Being Moderated
    Hello All

    Please let know if you have any thoughts

    Regards
    DR
  • 2. Re: Revenue Split based on Tasks
    Dina Rotem Guru
    Currently Being Moderated
    Hi

    You could fund the project at top task level.
    The approved revenue budget need to have budget lines by top task.
    The approved cost budget should have budget lines at top task level.

    Assuming that is you setup, you could create a billing extension that will calculate the percent spent of each top task, and multiply it by the revenue budget (baselined fund) of the top task. That will give you the accumulate revenue of each top task. The extension will then create a separate revenue event for each top task for the amount of accumulated revenue minus the prior total revenue if the top task.

    Dina