6 Replies Latest reply: Feb 4, 2013 3:36 AM by 988908 RSS

    activities dates from "status" started and finished; to their relationships

      I have revieved a schedule from another company to use as a basis for the one I am to create. When the schedule was originally created the scheduler was implemented some of the activites with "started and finished" dates under the "status" bar. I have removed the "started and finished" check marks assuming that the activities would now be sequenced/scheduled according to their assigned predecessor relationships but they are not falling in place as they should. Any recomendations?