    in-transit lead time while calculating suggested start date

    VCP Functional
      Hi All,

      This is regarding IR/ISO flow with in-transit lead time setup. I have set this lead time as 10 days along with following other lead time values.

      Item     X, Qty = 4, Intransit LT = 10 days, Pre processing =2 , Processing = 75, Post processing= 1, Plan run date = 13 Feb 13, Plan type = Unconstrained, Apps Version = 11.5.10

      With it is showing following data on supply/demand screen..

      Due Date = 30 Mar 13     (Date derived from top level independent demand like SO demand)
      Dock Date= 29 Mar 13     (= Due date – post processing LT = 30 Mar 13 – 1day = 29 Mar 13)
      Start Date     =19 Mar 13     (= Dock date – intransit LT = 29 Mar 13 – 10 days = 19 Mar 13)
      Order Date     =19 Mar 13      (= Start Date – pre processing LT = 15 Mar 13 – 2 days = 13 Mar 13 )

      Here I am not able to understand why is considering intransit LT while calculating start date. It should consider processing LT = 75 days..

      Is here something wrong here ?

      Thanks in advance,
      Dipak