Planning Unit - Changing Days to Hours

990590 Newbie
Currently Being Moderated
The project I am working in started with Engineering work, scheduled in days. I have added the Construction portion later, which needs to be scheduled in hours. How do I do this within the same schedule without affecting the previous work? I'm working in Primavera P6.1.