Scheduling Options under Routing

DivyaB Newbie
Currently Being Moderated

I would like to know if we can input Resource Offset % and if the system will honour it correctly. As per standard functionality the system automatically calculates both Lead time % and Offset % on selecting Compute Lead.

The Given scenario is to initiate the second operation at 50% completion of the first operation. Suppose if my manufacturing lead time is 3 days with 3 operations, then the system will always schedule the second operation on 2nd day but in practice I want to schedule the same on the very first day.


I understand that with scheduling options like 'Next' or 'Prior', I can start the operations in parallel but that is not what I intend to do.


Thanks.