1 Reply Latest reply: Jul 31, 2013 2:48 PM by MichaelRidino RSS

    Help With Budgeted Labor Units vs Estimated Labor Units




      THis is my first time usiing this group but my quesiton is probably pretty easy.

      I inherited two schedules - both use the same calendar and both are set to "fixed units" for duration types.


      When I add a task in one schedule the budgeted and remaining labor units automatically default to the same (i.e budgeted = remaining)

      In the other schedule however I have to manually overwrite both the budgeted and remaining to be equal in the status page.


      Not sure why this happens is there anyway to make Budgeted and remaining labor units always equal for baselining purposes?