    P6 Report - Filter based on activity dates

    46fd2f04-96be-4265-a07d-5edfe77b156c

      Good morning,

       

      I'm working on a report that should include all the activities in a project that respect the following condition:

      Finish date > BL1 finish date + 3 months

       

      As i can see I can compare a date with a standard date variable (Earliest project start, Latest project finish etc...) but i can't compare two date attributes.

       

      Is it possible to define new date variables?

       