1 Reply Latest reply: Mar 22, 2014 1:58 PM by Abhishek Sharma - Wipro RSS

    Release from Planner's workbench auto-triggers WIP Mass Load, how do we restrict

    254242b6-66f6-4f60-a719-4e23366cd204

      **Re-posting as members were not able to reply to the post**

       

      Hello All,

      To achieve some client specific functionalities we do not wish the WIP Mass load program to be automatically triggered in ERP instance when a planned order ( WIP Job) is released from ASCP Planner's workbench. So far, I could notice that either WIP Mass Load or Requisition Import is automatically triggered when a planner order is released from ASCP workbench ( Implement as Discrete job or PR). Is there some profile which controls this? or this is the expected functionality wherein the data interfaced to ERP tables is immediately processed.

       

      Any pointers will be highly appreciated.

       

      Regards

      JC