      Hi ,

       

      we have hyperion planning 11.1.2.2  and using calc manager for business rules. I needed to migrate them from QA to Prod.

      QA calc manager shows 20 essbase variables but after migration to prod,   in prod calc manager I see only 2 essbase variables.

      I checked through prod EAS and  noticed at prod essbase level, 20 variables are there so all the prod rules are getting validated after migration but my question is ..why all 20 variables are not appearing in prod calc manager list as they appear in QA calc manager list?

       

      I used planning application schema migration for this purpose and everything else looks ok .Is there something that I need to do for calc manager variable migation?

      plz help.

       