    Lag duration in days does not match 4x10 Calendar

    Steve Montgomery

      My schedule calendar is 4x10 (4-days per week, 10-hour days). I set the Time Periods Hours/Day to 10.0 (see below). But for some reason the lag in my schedule reverts back to an 5x8 (5-days per week, 8-hour days) calendar. In the below screen shot my 30-hour lag registers as 3.75-days, and not 3-days.

       

      Is something wrong with my schedule set up? Why is lag measured in 8-hour per day increments when my calendar is 4x10?

       

      Any thoughts?