10 Replies Latest reply: Mar 4, 2009 5:55 PM by 690399 RSS

    Remaining Duration & Hours per Time Period

      When I have a schedule with activities that have an 8 hr /
      day calendar, and a 10 hr / day calendar the finish dates
      on the activities seem to be right, but the remaining
      duration seems to be calculated off of the hours per time
      period (Hrs/TP) in user preferences.
      />So, what is the point of remaining duration
      calculating of to the Hrs/TP, and not the activates

      And how can I have a
      schedule with different calendars and have the remaining
      duration appear correct?