Remaining Duration & Hours per Time Period

690399 Newbie
Currently Being Moderated
When I have a schedule with activities that have an 8 hr /
day calendar, and a 10 hr / day calendar the finish dates
on the activities seem to be right, but the remaining
duration seems to be calculated off of the hours per time
period (Hrs/TP) in user preferences.
<br
/>So, what is the point of remaining duration
calculating of to the Hrs/TP, and not the activates
calendar.

And how can I have a
schedule with different calendars and have the remaining
duration appear correct?