    Best way to assign PM PC resources throughout the Project duration

    723194
      Which is the best activity type (LOE or WBS Summary) on which Project Mangers and Coordinators should be assigned for the entire project duration? and Why?? I currently assign PM and PCs on LOE and it creates problems while changeing resources from Roles. e.g. Replacing PM resource on active Project and changing budgeted and actuals hrs