0 Replies Latest reply: Jul 13, 2011 4:30 PM by 875354 RSS

    Seeking a solution to a Primavera .xer export error

      The problem: When an .xer export from Primavera Enterprise P6 is compared to the original, all the EVM data (hours / material costs / dates) matches up with the exception of the Planned values (BCWS) for nearly 25% of the tasks. The .xer export is being analyzed on a stand-alone PC with a valid and current copy of Primavera P6. This has been a repeated problem and it is occurring on more than one project. The P6 settings on the stand-alone PC are the same as the Enterprise version.

      Has anyone else experienced this problem? What did you discover as the cause? How did you fix it?