Discussions
Read on for the latest updates including:
• Agenda Builder launch
• SuiteWorld On Air registration
• New NetSuite Prompt Studio Contest
• And more!
Check out this thread to learn more!
Project Task Workflow
Hello all!
I started this project last summer but due to budget & time constraints I had to shelve it for a while. Now it's a priority and I'm running into a roadblock - here's the story:
I have created a workflow that will create project tasks upon creation of a new project based on various criteria. So far, creating the project task is not a problem, and is working the way I need it to.
However, I can't seem to trigger the "Assigned To" values with the workflow. It looks like the required fields are Assigned To, Estimated Work and Unit Cost which I would assume would allow for assignment of a resource. I've tried entering a number of values for these fields/columns, with no success. Also, "unit cost" is not an option to set, so I've tried both "cost" and "base cost". In any event, no luck.