Join us for complimentary one-day events around the world and step into a future fueled by AI and limitless potential. Explore new breakthroughs, sharpen your skills, and connect with experts who are shaping what’s next. Experience bold keynotes, interactive learning, and connections that span the global NetSuite community. Discover what's next at SuiteConnect Tour 2026.
NetSuite Manufacturing Enhancement 2013.1
Hi,
Did anyone implement Manufacturing Enhancement in 2013.1?
I found few bugs in system and did not get satisfactory answer from support.
Example:
1. System did not check operation sequence. Eg sequence 10, 20,30 but user can enter completion for 20 without 10
2. Not able to have variance for Estimated hours and Actual hours in operation. Eg if Work Order qty=100 and Estimated hour is x. When user amended the setup or run hours in enter operation, the Estimated hour x will be overwritten by y which is user entered as such there is no difference for Estimated hours and Actual hours.
3. Unknown work center calendar preference to follow. Eg someone told me is based on Home >Set Preference of the creator of Manufacturing Work Center but in SuiteAnswer, it says follow default work calendar.