I'm really not sure how to handle this. Let me explain exactly what I'm dealing with:
[LIST=1]
[*]We created a Purchase Order for qty. 1008 serialized widgets
[*]We supplied materials to build qty. 1009 serialized widgets
[*]Vendor created qty. 1009 serialized widgets
[*]Vendor delivered qty. 1005 serialized widgets that work and 4 that are broken.
[*]We received (Item Receipt) qty. 1005 serialized widgets
[*]Vendor invoiced for qty. 1008 serialized widgets.
[/LIST]
To summarize, we ordered 1008, they build 1009, delivered 1009 (4 of which are broken) and invoiced us for 1008.
I don't know the correct way to handle this. Do I update our PO for qty. 1009 and receive ALL delivered product, then request a credit for the faulty 4 units?
Should I receive only the working widgets, request an adjustment to the invoice and close the PO?
Is it possible to revieve a larger quantity on a PO than was originally ordered?
I don't want to lose the history of the 4 bad widgets (they are serialized) so my instinct is to do the following:[LIST=1]
[*]adjust the po to 1009
[*]alert the vendor of the adjusted qty and request a revised invoice
[*]receive ALL units
[*]move faulty units to "bond" location (so they aren't sold)
[*]request credit for faulty units from vendor
[/LIST]
Your help will be very much appreciated!
-Steve