I have a question about the execution of the project with the backward scheduling method.
In the environment are activated Project Accounting and Management, Advanced Billing and Advanced Financials. After enabling Planned Work, I created the project with BWS below and set a baseline.
Problem 1
I enter 32 hours of actual work instead of planned 16 hours for billable item (with timesheet input), that logically should move start of my Task 1.2 to the 17.01, because it has dependency FS with Task 1.1.
I expect that if I record 2 extra days against Task 1.1 (15 and 16.01) in Time Tracking, NetSuite advances the start and end dates of Task 1.2, and all tasks that depend on Task 1.2, by 2 days. (that is how I understand written Help Center instructions https://5033030-sb1.app.netsuite.com/app/help/helpcenter.nl?fid=section_n1191698.html)
But still, in Planning and Tracking View, as well as in Gantt Chart I see only originally planned dates.
Problem 2
My problem is that I only can use Constraint Type “As Late As Possible” because dependencies between tasks in our case are critical (I have sequence predecessors/descendants that I need for recalculation of further tasks dates if change happens). The only other Constraint Type on the task level that is listed is Fixed Start and breaks my dependencies.
Is any possibility to give for a task with 8 hours more than 1 day without making it with the working calendar? Lag Time for Predecessor is not helpful in combination with the Backwards scheduling method right, because is recalculates earlier task start date, that with the on-going project in progress already doesn’t make sense.
General questions
a) What is the best practical way to track tasks without Assigned resources if Allocation management is not purchased (we have a really big scope of tasks)?
b) Does NetSuite provide a possibility to make custom statuses for Project Tasks and Milestones?
Thanks in advance.