Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Update: Narrative Insights has been restored and is now available.
Narrative Insights is Temporarily Unavailable due to an Infrastructure Issue. Learn how This Impacts Your Account and What to Expect While the Feature is Disabled.
Narrative Insights is Temporarily Unavailable due to an Infrastructure Issue. Learn how This Impacts Your Account and What to Expect While the Feature is Disabled.
Tracking projects without time entries (statuses/overwrite actual time)
Is this possible with Project Management in standard to track projects and change % completion without entering actual time in the system against the project? (or overwrite actual work for each task)
My aim is to get percent work complete % according to task statuses and still assign generic resources to the tasks for planning purposes.
Help Center says that when the status of all tasks is Completed, percentage work complete % should show 100% and the same for individual tasks: when the task status is Completed, the percentage is 100%.
https://5033030-sb1.app.netsuite.com/app/help/helpcenter.nl?fid=section_3740077129.html
So I expect Percent work complete to be 100% in the screenshot below:
2