Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Project Task Import - multiple resource assignees
We are using quite a few features of Netsuite Projects including, projects, Project management, advanced project profitability and several suite apps.
We are using Activities > Scheduling > Project Tasks > Import to import tasks. Each task could have multiple resources assigned.
Our issue: when we import the tasks with multiple resource assignees, it is creating new tasks for every employee assignment, which is not what we want. Has anyone been able to import the tasks and the assignees so that it is in a one to many arrangement?
Should we import the tasks first and then try to do the assignment in a second load?