New location missing in MRP workbench view
We created a new location which now has item demand plans loaded, as well as inbound shipments and in-transit transfer orders. Everything in- and out-bound from the location seems clear and clean. However, in Planning Workbench, this location is not appearing alongside other locations in the subsidiary. Has anyone run into…
-
Is there a way to make MRP / Planning Workbench consider a Work Calendar?
We would like that the MRP calculations took into account that Holidays and weekends, which would be indicated in a Work Calendar, are not to be considered as part of Item/Vendor Lead times for planning and expected receipt date purchases, meaning, if I need something on Sept 18 2023, and my purchase/vendor lead time is 5…
-
Workbench Work Orders Past Due
Hi Everyone! I'm learning some of the fundamentals of MRP in NetSuite, and have been starting to get a general understanding of the workbench. I'm encountering an issue currently with the workbench and work orders generated from outsourced Purchase Orders that are past due where they aren't being taken into account into…
-
Clarification Needed on Record Limit in Supply Plan Definition and Planner Workbench
I am currently encountering an issue in the supply plan definition process where I'm limited to managing only 100 records. This constraint is impacting my ability to efficiently carry out planning activities. Could you please confirm if there is indeed a set limit on the number of records in the supply plan definition and…
-
Configure MRP To Avoid Weekends/Holidays
Hi NS Community, Has anyone found a way to configure the NetSuite MRP feature to avoid weekends and holidays. For example, MRP may suggest that we schedule a PO to come in on a Sunday and thusly plan production to occur that following Monday. However, in reality the supplier will arrive on Monday and will be ready for…
-
Purchase order created from Planning workbench does not add landed cost template
Hi There, When creating a purchase order, the landed cost template appears on the item line level. However, in Supply planning workbench, when a purchase order is created, it does not add the landed cost template for the item. Is there something in the setup where I can change it so that it works the same as crating manual…
-
Query Regarding Allocated Stock in Supply Planning Workbench
I am writing to seek clarification on an observation in the Supply Planning Workbench. It appears that the system does not account for Allocated Stock in its calculations and planning. Could you please shed some light on why Allocated Stock is not considered in the Supply Planning Workbench? Additionally, if this is a…
-
Open Transfer Orders not visible on Planning Workbench
Hello, We are setting up Supply Planning. On the Planning Workbench I expect to see open transfer orders (TOs that are in Pending Fulfillment/Pending Receipt Status) in the ON-ORDER column for the items, but I am not seeing any data in this column. What setting or data point needs to be set to have a quantity come through…
-
Planning Workbench
Is it possible to segment the Planning Workbench to display data by individual sales orders, or alternatively, run the MRP based on each day's sales orders for more precise planning?
-
How to customize Planning Workbench view?
Does anyone know that what is the availability to change the view in planning workbench? It seems that only possibility is to make different planning workbench views where can add-on some pre-defined filters and use saved search with item's information , but not add any new filters. Now in the supply view or in the…