Categories
- All Categories
- Oracle Analytics and AI Learning Hub
- 54 Oracle Analytics and AI Sharing Center
- 26 Oracle Analytics and AI Lounge
- 311 Oracle Analytics and AI News
- 57 Oracle Analytics and AI Videos
- 16.4K Oracle Analytics and AI Forums
- 6.7K Oracle Analytics and AI Labs
- Oracle Analytics and AI User Groups
- 117 Oracle Analytics and AI Trainings
- 24 Oracle Analytics and AI Challenge
- Find Partners
- For Partners
Welcome to the Oracle Analytics Community: Please complete your User Profile and upload your Profile Picture
PPM-Project Budget to derive Budget Burdened Cost
User_YDJ78
Rank 1 - Community Starter
Hi Team,
I am using this subject area to derive project, along with project start and end dates and budget burdened cost
This works fine for current baseline budget cost.
However, when I change the date parameters the cost and dates doesn't change.
Attached screenshot for reference,
For example : Project number : RE0608, which has 3 different budget versions and I need to extract the cost for only one year.
Questions
- Am I using the correct dimensions, fact/measure, if not, can anybody guide me to right attributes or do I have to create custom calculation logic.
- I have to derive project revenue from GL (as it is not managed in PPM), which subject area to use
Tagged: