PPM-Project Budget to derive Budget Burdened Cost

Question
3
Views
0
Comments

Hi Team,

I am using this subject area to derive project, along with project start and end dates and budget burdened cost

This works fine for current baseline budget cost.

However, when I change the date parameters the cost and dates doesn't change.

Attached screenshot for reference,

For example : Project number : RE0608, which has 3 different budget versions and I need to extract the cost for only one year.

Questions

  1. Am I using the correct dimensions, fact/measure, if not, can anybody guide me to right attributes or do I have to create custom calculation logic.
  2. I have to derive project revenue from GL (as it is not managed in PPM), which subject area to use