hi,

We have DAC 11g. While running DAC load plan, we found that multiple sets of mapping been triggered into single load plan.

i.e. if we have 10 infa mappings inside 1 DAC load plan , then DAC triggers multiple sets of mappings inside single load plan, so same 10 mappings been triggered 2-3 times, total 20-30 mapping gets triggered. 1st set works fine & completes but other set of mapping get stopped. so 1-10 mapping get completed & 2nd set from 11-20 goes into stopped status.

found below errors in log file

Task 'SIL_Stage_GroupAccountNumberDimension_FinStatementItem' already included in the nodes list.

Update Row into Run Table:ORA_R1213_Flatfile:DataWarehouse has been already notified by PLP_AbsenceEventFact_PositionHierarchy_Update:DataWarehouse:DataWarehouse

QUERY_INDEX_CREATION:DataWarehouse:DataWarehouse has been already notified by PLP_AbsenceEventFact_PositionHierarchy_Update:DataWarehouse:DataWarehouse

Request to start workflow : 'PLP_WorkforceEventFact_Month with the instance name PLP_WorkforceEventFact_Month' has completed with error code 0

please