Summary
We had a scheduled that ran an hour early after daylight savings time ended
Content
There is a scheduled report job that runs at 5:30am each wednesday. With daylight savings time ending this past weekend, the job ran at 4:30am instead of 5:30am. The schedule was set up to run at 5:30 Eastern Time, but it doesn't say EST/EDT. I did update the start date to next week in an effort to get it to run back at 530am but wasn't sure if anyone had any advise to ensure that the system runs this at the same time no matter daylight savings time.
This report is based off of an HCM extract in the system, and that process worked as expected with the daylight savings time change, only BI had the issue.
Version
19C