Hi,

PBCS

As standard I have period as a dense dimension.

I have a business rule that fixes on periods X:Dec, where X is changed each month.

Inside the business rule there is IF logic using current member to examine what the month is and applying subtly different results for each month.

All of the data is level0 data in the rule.

Am I guaranteed that in all circumstances the data will be evaluated in month order (Jan to Dec) if that is the order of the dimension members in the dimension, or if not, is there a way I can guarantee that they will be evaluated in that order, as each subsequent month needs to use the result of months prior to that in its calculation.

Ideally I do not want to use a loop or a fix statement beyond the initial fix.

i.e. (Simplified)

FIX (working, basedata, local, {ForecastPeriod})

IF (@ISMBR("Feb"))

            &currforc = "Actual"->"Jan";

        ELSEIF (@ISMBR("Mar"))

            &currforc = ("Actual"->"Jan" + (2 * "Actual"->"Feb")) / 3;

        ELSEIF (@ISMBR("Apr"))

(etcetera with subtly different non-formula friendly formula for the rest of the months)

END FIX;

Thanks in anticipation of your input.

Tagged:

Best Answer

  • user9928941
    user9928941 Member Posts: 222
    edited Apr 18, 2018 3:39PM Answer ✓

    It would. Unless you have a different execution result . You mentioned Jan-Dec as the period outline order and the calcscript to take in a member which would return the range from (Jan:Dec) through (Dec:Dec).

    So the FIX should loop over one period at a time.