Robeen
Robeen Member Posts: 2,179 Silver Badge
edited Feb 4, 2020 4:32AM in Recovery Manager (RMAN)

Oracle DB 12.1.0.2

Solaris 14

RAC 2 nodes

Hi,

As shown below, my full backup starts at 21:02 and ends at 06:11. Archivelog backup was scheduled on an hourly schedule which starts at 4 am as shown below. Will DB be still recoverable despite archivelog running in parallel with full backup?

pastedImage_0.png

Regards,

Joe