Hi,
Hyperion planning version 11.1.2.4.500
All components are one server.
Just for clarification and diagnose purpose i have few questions regarding database refresh and executing calculation script via planning.
1 - When i ran a rule from data form, planning sends that script to essbase and then essbase performs all the calculations.
-After executing the command if my network crashes will the script get stopped? will it get error out? because of no connectivity between client machine (from where i ran the rule) and server?
-Would Essbase have any effect?
2-Same as above but for essbase refresh from client machine using hyperion planning.
Regards