    P3.1 upgrade

    751026
      Is P3.1 upgradeable to P6? I dont know if this is a silly question but I need some advice on this.

      Thanks,

      Tony
        • 1. Re: P3.1 upgrade
          Akhtar Khan
          P3.1 and P6 are different animals,
          • 2. Re: P3.1 upgrade
            cruz878
            P3.1 is not directly upgradeable to P6. What you can do is stand up a P6 database and import in all schedules that you still wish to work with in P6. There are some caveats to the import process and certain data is not transferred (I believe there is a KB article outlining the details of what does not come over). Depending on how long your P3 projects are running it may be best to continue those in P3 and start any new projects in P6.