Is P3.1 upgradeable to P6? I dont know if this is a silly question but I need some advice on this.

Thanks,

Tony
  • 1. Re: P3.1 upgrade
    Akhtar Khan Newbie
    Currently Being Moderated
    P3.1 and P6 are different animals,
  • 2. Re: P3.1 upgrade
    cruz878 Journeyer
    Currently Being Moderated
    P3.1 is not directly upgradeable to P6. What you can do is stand up a P6 database and import in all schedules that you still wish to work with in P6. There are some caveats to the import process and certain data is not transferred (I believe there is a KB article outlining the details of what does not come over). Depending on how long your P3 projects are running it may be best to continue those in P3 and start any new projects in P6.