0 Replies Latest reply on Mar 9, 2010 2:05 PM by Stick

    R12 PO Inspection vs. Quality Skip Lot

    Stick
      We have been performing PO inspections without the Quality module for over 10 years. There is project to move many of our key suppliers to an Evaluated Receipt Settlement program. The accounting folks want to throw these suppliers into some sort of Skip Lot process. However it appears that to go in this direction all Inspection Required receipts will now have to have a Quality Plan associated to it. Is this true? Is there anyway to commingle the two inspection methods?