    P3 not following successor rules and changing dates

    771497
      See the pictures for reference.

      before

      after

      Why is it changing the construction activities so they strart at the beggining when they are supposed to be succesors of "Construction"
        • 1. Re: P3 not following successor rules and changing dates
          p3_scheduler
          user13064368,

          At first glance, your issue seems to be a simple relationship error.

          Are you sure that the successors to "#1370 Construction Starts" are the activities # 1080, 1070, 1110 ?? Can you display the logic ties on your next screen shots?

          Usually, if an activity has no predecessor it will get slammed against the data date after calculating the schedule. Looks like those activities have no valid predecessor (#1370 Construction Starts).



          Hope this helps,